CONTRACT NO. 1 — GENERAL CONSTRUCTION
Marchuska Brothers Construction, LLC: $810,035
Parsons-McKenna Construction: $696,100
Bellows Construction Specialities, LLC: $806,102
J.D. Taylor Construction Corp.:$771,000
Bouley Associates, Inc.: $723,000
GM Crisalli & Associates, Inc.: $739,950
James & Son Construction Co., Inc.: $656,000
MCK Building Associates, Inc.: $785,000
CONTRACT NO. 2 — PLUMBING
HMI Mechanical Systems: $96,500
Daniel D’Amico: $116,420
Avolio Brothers: $92,505
Brosh Mechanical, Inc.: $104,000
Siracusa Mechanical, Inc.: $119,740
CONTRACT NO. 3 — GEOTHERMAL CONSTRUCTION
American Auger & Ditching Co.: $29,480
Nothnagle Drilling, Inc.: $54,000
CONTRACT NO. 4 — MECHANICAL
HMI Mechanical Systems: $133,500
Tag Mechanical: $132,000
King & King Mechanical: $151,129
Airside Technology: $169,878
Airtech Heating & Air Conditioning Systems: $144,715
Daniel D’Amico: $165,600
CONTRACT NO. 5 — ELECTRIC
Knapp Electric: $143,200
Beken Contracting: $169,000
Edgeline Electric: $143,400
Patricia Electric: $164,000
TOTAL APPARENT LOW BIDDER PROJ. COST: $1,053,185
About two dozen local and regional contractors attended the opening of construction bids for the new village hall renovation project on Wednesday, Nov. 12, to learn who is most likely to be hired for the five different contracts necessary for the work.
Four of the five contracts – general construction, plumbing, mechanical and electric – had four or more bids submitted for consideration, while the fifth contract – geothermal construction – had only two. Some of the bids differed by hundreds of thousands of dollars, others by only hundreds of dollars.
“We got good bids as far as competition,” said Mayor Marty Hubbard at the end of the bid opening meeting. “It takes all the uncertainty of the value out of it.”
All the members of the New Village Hall Steering Committee, which is overseeing the renovations to the Fennell Street fire station to turn it into the new village hall, were present for the bid opening, as was project architect Connie Brace.
The apparent low bidders for each of the five contracts were:
—General construction: James & Son Construction Co., Inc., of Skaneateles, $656,000
—Plumbing: Avolio Brothers, of Norwich, $92,505
—Geothermal: American Augur & Ditching Co., of Constantia, $29,480
—Mechanical: Tag Mechanical, of Syracuse, $132,000
—Knapp Electric, of Auburn, $143,200
The total cost of the lowest base bids for all five contracts is $1,053,185. The sale proceeds for the current village hall building at 46 E. Genesee St., which will be used to fund the renovations, was $830,000. The village has already received or is awaiting reply for a number of state and federal grants, however, to offset the cost of the project.
The village board will discuss the bids at an operations meeting scheduled for 7:30 p.m. Tuesday, Dec. 18, at village hall. Hubbard said he is hopeful that on that day the village will also receive a response from state officials about a major grant the village applied for.
Jason Emerson is editor of the Skaneateles Press. He can be reached at [email protected].